Section 209.53. Extension of time to complete project; request.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • (1) A request for an extension  of  time  for   completion  of  a project, not to exceed 1 year, including the installation of all  tangible personal property, provided for in section 15(2) 1974 PA 198, MCL 207.565(2), shall be filed with the local unit of government within the final year of the 2-year construction period.

    (2)    Upon receipt of a request for extension, the local unit may do any of the following:

    (a)  ) Deny the request.

    (b)   Approve the request with no change  in  the  ending  date  of  the certificate that was issued.

    (c)   Approve the extension of time for the completion of the project and a revised ending date on the certificate, not to exceed 1 year.

    (3)   A request for an extension of time for the completion of a project shall be filed with the commission by the certificate holder and shall be accompanied by a resolution of approval adopted by the local  governmental unit.

History: 1982 AACS; 2009 AACS; 2010 AACS.