Section 336.1210. Renewable operating permits.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • (1) A person shall not operate any emission units located at a stationary source required to obtain a renewable operating permit under R 336.1211, except in compliance with all applicable terms and conditions of a renewable operating permit, unless a timely and administratively complete application for a renewable operating permit has been received by the department in accordance with the following provisions of this rule. The ability to operate the emission units at a stationary source while a timely and administratively complete application is being reviewed and acted upon by the department shall be referred to as the "application shield." The application shield provided by this subrule shall not apply if an application submittal is not timely under the applicable provision of subrules (4) to (9) of this rule or administratively complete under subrule (2) of this rule or an additional information submittal is not timely or complete under subrule (3) of this rule. The loss of the application shield after the applicable time specified in this rule for a person to have filed a timely and administratively complete application for a renewable operating permit is grounds for enforcement action under the act. Any enforcement action pursuant to loss of the application shield shall consider the time period between the applicable deadline and when a person actually submits the required administratively complete application or additional information.

    (2)     An application submittal, including an application submittal for renewal or modification of a renewable operating permit, shall be considered an administratively complete application if it contains reasonable responses to all requests for information in the permit application form required by the department and a certification by a responsible official which states that, based on information and belief formed after reasonable inquiry, the statements and information in the application are true, accurate, and complete. The application form required by the department shall be consistent with the requirements of section 5507 of the act, except as provided for general renewable operating permits under R 336.1218. The application form shall also require a certification of compliance with all applicable requirements, a statement of methods used for determining compliance, including a description of monitoring, recordkeeping and reporting requirements, and test methods, and a statement indicating the stationary source's compliance status with any applicable enhanced monitoring and compliance

    certification requirements of the clean air act.  All of the following provisions apply to the administrative completeness of an application for a renewable operating permit:

    (a)    On and after November 1, 1995, the department shall notify the person who submitted the application for a renewable operating permit and the responsible official, in writing, regarding the administrative completeness of the application submittal. If the application submittal is considered not to be an administratively complete application by the department, then the notification shall specify the deficiency and all supplemental materials required for an administratively complete application. A person's response to a notification by the department of the incompleteness of an application shall include all of the supplemental materials requested by the department in the notification and a certification by the responsible official which states that, based on information and belief formed after reasonable inquiry, the statements and information in the response are true, accurate, and complete.  All of the following provisions apply to department notification:

    (i)   If the department fails to notify a person that an application submittal, including the submittal of any supplemental materials requested by the department under this subdivision, is not administratively complete by the following deadlines, then the submittal shall be considered an administratively complete application as of the date the department received the submittal or the supplemental materials, whichever is later:

    (A)   By January 5, 1996, or within 60 days of the date the department receives the submittal, whichever is later, if the submittal is received on the paper forms specified by the department.

    (B)   By November 15, 1995, or within 15 days of the date the department receives the submittal, whichever is later, if the submittal is received in an electronic format specified by the department.

    (ii)    If a person submits all of the supplemental materials identified in a notification from the department under this subrule, then the application shall be considered administratively complete.

    (iii)    Except as provided in paragraph (i) of this subdivision, the date the department receives all information required for an administratively complete application, including all supplemental materials requested by the department under this subdivision, shall be the date of receipt of the administratively complete application.

    (b)   Any person who fails to submit any relevant facts or who has submitted incorrect information in an application for a renewable operating permit, including an application for renewal or modification of a renewable operating permit, shall, upon becoming aware of the failure or incorrect submittal, promptly submit all supplementary facts or corrected information. Each submittal of any relevant facts or corrected information shall include a certification by a responsible official which states that, based on information and belief formed after reasonable inquiry, the statements and information in the submittal are true, accurate, and complete.

    (c)    A person shall promptly provide any additional information necessary for an administratively complete application for any applicable requirements to which the stationary source becomes subject after the date that the person submitted the administratively complete application, but before release of a draft renewable operating permit for public participation under R 336.1214(3). For administratively complete applications submitted under subrule (4)(e) or (f) of this rule, the information required by this  subrule  may  be  maintained  by  the  person  and  submitted  to   the  department   in

    accordance with the following schedule, unless the department specifically requests that information by an earlier date under subrule (3) of this rule:

    (i)   By January 1, 1998, for all applications for a renewable operating permit required to be submitted under subrule (4)(e) of this rule and for all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date from October 16, 1996, to December 15, 1996.

    (ii)   By January 1, 1999, for all applications for a renewable operating permit required to be submitted under subrule (4)(f) of this rule and for all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date from December 16, 1996, to February 28, 1997. Each submittal of any additional information shall include a certification by the responsible official which states that, based on information and belief formed after reasonable inquiry, the statements and information in the submittal are true, accurate, and complete.

    (3)   After an application for a renewable operating permit has been determined by the department to be administratively complete, the department may require additional information, including information that was not requested on the application form. For the purpose of this subrule, additional information means information necessary to evaluate or take final action on the application, information needed to determine the applicability of any lawful requirement, information needed to enforce any lawful requirement, information needed to address any applicable requirements to which the stationary source becomes subject after the date that the person submitted the administratively complete application, but before release of a draft renewable operating permit for public participation under R 336.1214(3), or information needed to evaluate the amount of the annual air quality fee for the stationary source. A person's response to a request for additional information by the department shall include all of the information requested by the department in the request and a certification by a responsible official which states that, based on information and belief formed after reasonable inquiry, the statements and information in the response are true, accurate, and complete. The person who submitted the application for a renewable operating permit for a stationary source shall furnish, within 30 days of the date of the request, any additional information requested, in writing, by the department, except as follows:

    (a)    A 30-day extension for a response shall be granted if the person requests that extension, in writing, during the initial 30-day time period.

    (b)   The person may request a longer period of time, in writing, specifying the reasons why 60 days was not reasonable for submitting the requested information.

    (c)   The department shall provide written notice to the person of the date of expiration of any time period for submittal of all requested additional information as a part of any request for additional information or upon granting a request for an extension. Failure to submit additional information that has been requested in writing by the department by the expiration of the time period specified for response results in the loss of the application shield specified in subrule (1) of this rule.

    (4)        For  a  stationary   source    that   is   defined    as     major   source   under R 336.1211(1)(a)(i) to (iii) on or before July 26, 1995, an administratively complete application for a renewable operating permit shall be considered timely if it is received by the department on or before the following deadlines:

    (a)   By February 29, 1996, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 0600-0999 (agricultural services), 1500-1799 (construction), 1800-1999, 2000-2039 (food), 2100-2399 (tobacco and textiles), 2400-2499 (lumber and wood), 2950-2999 (asphalt), 3270-3289 (concrete, lime and gypsum products), 5000-5499 (services), or 5600-7499 (services). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (b)   By May 15, 1996, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 3000-3099 (rubber and miscellaneous plastic), 5500-5599 (auto dealers and gas service), or 7500-7599 (auto repair). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (c)   By July 30, 1996, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 3400-3599 (fabricated metal). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (d)   By October 15, 1996, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 1300-1399 (oil and gas), 2051- 2099 (bakeries and food), 2500-2599 (furniture), 2650-2699 (paper products), 3600-3699 (electronic), 4000-4899 (transportation), 7600-7999 (services), 8100-9999 (services). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (e)   By December 15, 1996, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 1000-1299 (mining), 1400- 1499 (nonmetallic mineral mining), 2040-2050 (grain mills and cereal), 2700-2799 (printing), 3100-3199 (leather), 3200-3269 (stone, clay, and glass), 3290-3299 (nonmetallic mineral products), 3700-3710 (transportation equipment), 3714-3799 (transportation equipment), 3800-3999 (miscellaneous manufacturing), 4900-4999 (gas, electric and sanitary services), 8000-8099 (medical). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (f)   By February 28, 1997, for a major source, as defined by R 336.1211(1)(a)(i) to (iii), with a standard industrial classification (sic) code of 2600-2649 (paper mills), 2800- 2899 (chemicals), 2900-2949 (petroleum refining), 3300-3399 (primary metal), 3711- 3713 (automobile and truck assembly). For a major source that operates under multiple sic codes, the sic code that resulted in the most actual emissions of air contaminants from the major source during calendar year 1994 shall be the sic code used for the purposes of this subrule.

    (g)   Notwithstanding the deadlines specified in subdivisions (a) to (f) of this subrule, a person who owns or operates 2 or more stationary sources that are subject to the provisions of this rule may request, in writing, an alternate schedule for submittal of

    timely and administratively complete applications for renewable operating permits for those stationary sources. The proposed schedule shall provide that administratively complete applications for the stationary sources shall be submitted between the dates specified in subdivisions (a) to (f) of this subrule. If agreed to in writing by the department, the alternate schedule shall be the basis for determining whether an administratively complete application is timely pursuant to this rule.

    (5)   For a stationary source that is defined on July 1, 2011 as a major source solely due to greenhouse gas emissions under R 336.1211(1)(a)(iv), an administratively complete application for a renewable operating permit shall be considered timely if it is received by the department on or before July 1, 2012.

    (6)       For  a  stationary   source    that   becomes     major   source,    as   defined   by R 336.1211(1)(a)(i) to (iii), after July 26, 1995, an administratively complete application shall be considered timely if it is received by the department not more than 12 months after the stationary source commences operation as a major source. For a stationary source that becomes a major source, as defined by R 336.1211(1)(a)(iv) for greenhouse gas emissions, after July 1, 2011, an administratively complete application shall be considered timely if it is received by the department not more than 12 months after the stationary source commences operation as a major source. For the purposes of this subrule, commencing operation as a major source occurs upon commencement of trial operation of the new or modified emission unit that increased the potential to emit of the stationary source to more than or equal to the applicable major source definition specified in R 336.1211(1)(a).

    (7)   For a stationary source that is an affected source under title IV of the clean air act, a complete permit application for an initial phase II acid rain permit shall be considered timely if it is submitted by January 1, 1996, for sulfur dioxide and January 1, 1998, for nitrogen oxides.

    (8)     For renewal of a renewable operating permit, an administratively complete application shall be considered timely if it is received by the department not more than 18 months, but not less than 6 months, before the expiration date of the current renewable operating permit.

    (9)   For a stationary source that is not a major source under R 336.1211(1)(a), but is otherwise subject to the requirements of this rule under R 336.1211(1), a complete application is considered timely if it is received by the department in accordance with the following provisions, as applicable:

    (a)   For an affected source under R 336.1211(1)(b), on or before October 1, 1997.

    (b)   For a solid waste incineration unit under R 336.1211(1)(c), within 12 months of the date of the promulgation of an applicable requirement under section 129(a) of the clean air act.

    (c)   For a municipal solid waste landfill under R 336.1211(1)(d), by whichever is the later of the following dates:

    (i)   November 1, 1998.

    (ii)     Within 21 months of the effective date of R 336.1931 for implementing the provisions of 40 C.F.R.  part 60, subpart Cc.

    (iii)      Within 15 months of the date the landfill becomes subject to any of the provisions of 40 C.F.R. part 60, subpart WWW.

    (10)   For modifications to a renewable operating permit, an administratively complete application shall be considered timely if it is received by the department in accordance with the time frames specified in R 336.1216.

    (11)   Failure to operate in compliance with all terms and conditions of an operating permit is grounds for enforcement action under the act, permit revocation or revision, or denial of a permit renewal application.

    (12)   Failure to halt or reduce an activity when necessary to comply with an operating permit is grounds for enforcement action.

    (13)   Submittal of a complete application for a renewable operating permit does not supersede or affect any requirements to obtain a permit to install under R 336.1201.

    (14)   A person who submits information to the department as a part of an application for a renewable operating permit under a claim of confidentiality, consistent with the requirements of the freedom of information act, 1976 PA 442, MCL 15.231 to 15.246, shall submit a copy of the information directly to the United States environmental protection agency.

    (15)   Except as provided in this subrule, the department shall take final action on each administratively complete application for a renewable operating permit, including an application for permit renewal, within 18 months after the date of receipt by the department of an administratively complete application. The department shall take final action on each timely and administratively complete application for first time issuance of a renewable operating permit for major sources, submitted under subrule (4)(a) to (f) of this rule, in accordance with the following schedule:

    (a)    By February 28, 1997, for all applications for a renewable operating permit required to be submitted under subrule (4)(a) and (b) of this rule and on all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date on or before May 15, 1996.

    (b)    By February 28, 1998, for all applications for a renewable operating permit required to be submitted under subrule (4)(c) and (d) of this rule and on all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date from May 16, 1996, to October 15, 1996.

    (c)    By February 28, 1999, for all applications for a renewable operating permit required to be submitted under subrule (4)(e) of this rule and on all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date from October 16, 1996, to December 15, 1996.

    (d)    By February 28, 2000, for all applications for a renewable operating permit required to be submitted under subrule (4)(f) of this rule and on all applications submitted under an alternate schedule under subrule (4)(g) of this rule with a submittal date from December 16, 1996, to February 28, 1997.

History: 1995 AACS; 1996 AACS; 1999 AACS; 2001 AACS; 2012 AACS.