Section 336.1214. Approval of a renewable operating permit.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • (1) After the department has received an administratively complete application and  all  additional  information   requested  by  the  department  pursuant  to R 336.1210(3) for a renewable operating permit, significant modification to a renewable operating permit, or the renewal of a renewable operating permit, the department shall prepare a draft permit and a report that sets forth the applicable requirements and factual basis for the draft permit terms and conditions. The report shall include citations of the applicable requirements, an explanation of any equivalent requirements or other changes included in the draft permit pursuant to R 336.1213(2), and any determination made pursuant to R 336.1213(6)(a)(ii) regarding requirements that are not applicable to the stationary source where the draft permit contains only a summary of the determination.

    (2)    The person who applied for the renewable operating permit shall be provided with a reasonable period of time, but not less than 7 days nor more than 30 days, to review and comment on the draft renewable operating permit, draft renewable operating permit significant modification, or draft renewable operating permit renewal before the start of the public participation procedure specified in subrule (3) of this rule. If the person and the department cannot agree on the terms and conditions of the draft renewable operating permit, the terms and conditions that the department believes are necessary to comply with the requirements of R 336.1213 shall be incorporated into the draft renewable operating permit and the report required by subrule (1) of this rule shall include a discussion of the person's objections.

    (3)      Except for modifications qualifying for administrative permit amendment procedures pursuant to R 336.1216(1) or minor permit modification procedures pursuant to R 336.1216(2), the draft renewable operating permit, draft renewable operating permit modification, or the draft renewable operating permit renewal shall be subjected to the following public participation procedure before the department submits a proposed renewable operating permit to the United States environmental protection agency for review pursuant to subrule (6) of this rule:

    (a)    The department shall provide public notice by publication in a newspaper of general circulation in the area where the stationary source is located or in a state publication designed to give general public notice. Notice shall also be provided to persons on a mailing list maintained by the department, including persons who request, in writing, to be on that list, and to any person who requests, in writing, to be notified of a permit action involving a specific stationary source.

    (b)   The notice shall set forth all of the following information:

    (i)   The name of the stationary source.

    (ii)   The name and mailing address of the responsible official.

    (iii)   The mailing address of the department.

    (iv)   The activity or activities involved in the proposed permit action.

    (v)   The emissions change involved in any permit modification.

    (vi)   The name, address, and telephone number of a representative of the department from whom interested persons may obtain additional information, including copies of the draft permit, the report required under subrule (1) of this rule, and, to the extent provided by the freedom of information act, 1976 PA 442, MCL 15.231 to 15.246, the application and any other materials available to the department that are relevant to the permit decision.

    (vii)   A brief description of the procedures to submit comments.

    (viii)    The time and place of any hearing that may be held, including a statement of the procedures to request a hearing, unless a hearing has already been scheduled.

    (c)   The department shall provide not less than 30 days for public comment and shall give notice of any public hearing not less than 30 days in advance of the hearing.

    (d)    The department shall keep a record of the commenter’s and the issues raised during the public participation process and the records shall be available to the public.

    (4)   The department shall give notice of each draft permit to any affected state on or before the time that the department provides notice to the public pursuant to subrule (3) of this rule, unless R 336.1216(2) requires the timing of the notice to be different. The department shall notify the administrator of the United States environmental protection agency and any affected state, in writing, of any refusal by the department to accept all recommendations for the proposed permit that the affected state submitted during the public comment period specified in subrule (3)(c) of this rule. The notice shall include the department's reasons for not accepting any recommendation. The department is not required to accept recommendations that are not based on applicable requirements.

    (5)   After the completion of the public participation procedure specified in subrule (3) of this rule and the review by affected states specified in subrule (4) of this rule, the department shall prepare a proposed renewable operating permit, proposed renewable operating permit significant modification, or proposed renewable operating permit renewal. If the proposed renewable operating permit differs from the draft renewable operating permit in response to substantial and relevant comments from the public or affected states, the person who applied for the renewable operating permit shall be provided with a reasonable period of time, but not less than 7 days nor more than 30 days, to review and comment on the changes before the transmittal of the proposed renewable operating permit to the United States environmental protection agency for review. If the person and the department cannot agree on the changes to the proposed renewable operating permit, the changes that the department believes are necessary to comply with the requirements of R 336.1213 shall be incorporated into the proposed renewable operating permit and the person's objections shall be included in the information transmitted to the United States environmental protection agency for review.

    (6)    Except as provided in 40 C.F.R.  70.8(a)(1) and (2), adopted by reference in R 336.1299, and as provided in R 336.1210(14), the department shall transmit a copy of each administratively complete application for a renewable operating permit, including any application for a significant modification to a renewable operating permit or for renewal of a renewable operating permit, all additional information submitted pursuant to R 336.1210(3), the report prepared pursuant to subrule (1) of this rule, and the proposed renewable operating permit to the United States environmental protection agency. The department shall not take a final action to issue a renewable operating permit until 45 days  after  the   United  States  environmental  protection  agency  has  received   all  the

    information specified in this subrule and subrule (4) of this rule. If the administrator of the United States environmental protection agency objects, in writing, to the renewable operating permit before the end of the 45-day review period specified in this subrule, the department shall not issue the renewable operating permit until the administrator's objection has been resolved. The department shall follow the procedure specified in 40 C.F.R. 70.8(c), adopted by reference in R 336.1299, to resolve the objection. The application shield provided by R 336.1210(1) shall continue to apply to the stationary source, consistent with the provisions of R 336.1210, until the department takes final action on the renewable operating permit.

    (7)     The department shall make a final decision to issue or deny a renewable operating permit, a significant modification to a renewable operating permit, or the renewal of a renewable operating permit after completion of the review by the United States environmental protection agency specified in subrule (6) of this rule. The final renewable operating permit shall contain all terms and conditions determined by the department to be necessary pursuant to R 336.1213, after consideration of all comments received during public participation pursuant to subrule (3) of this rule and affected state review pursuant to subrule (4) of this rule, including any terms and conditions necessary to resolve any objection by the administrator of the United States environmental protection agency pursuant to subrule (6) of this rule. The department shall transmit a copy of each final renewable operating permit to the United States environmental protection agency. A person aggrieved by the issuance, denial, modification, or renewal of a renewable operating permit may appeal the final decision as provided in section 5506(14) of the act.

    (8)    Any person may petition the administrator of the United States environmental protection agency to make an objection regarding a renewable operating permit pursuant to 40 C.F.R. 70.8(d), adopted by reference in R 336.1299. The petition shall be filed within 60 days after the expiration of the administrator's 45-day review period specified in subrule (6) of this rule and 40 C.F.R. 70.8(c), adopted by reference in R 336.1299. The petition shall be based only on an objection to the renewable operating permit that was raised with reasonable specificity during the public comment period provided for in subrule (3)(c) of this rule, unless the petitioner demonstrates that it was impracticable to raise the objection during the public comment period or unless the grounds for the objection arose after the public comment period. A petition for review does not stay the effectiveness of a renewable operating permit or its requirements if the renewable operating permit was issued after the end of the 45-day review period and before the department received an objection by the administrator. If the administrator of the United States environmental protection agency objects to the renewable operating permit as a result  of  a   petition  filed  pursuant  to  40 C.F.R.  70.8(d),  adopted  by  reference  in R 336.1299, before the department has issued the renewable operating permit, the department shall not issue the renewable operating permit until the administrator's objection has been resolved. The application shield provided by R 336.1210(1) shall continue to apply to the stationary source, consistent with the provisions of R 336.1210, until the department takes final action on the renewable operating permit. If the administrator of the United States environmental protection agency objects to the renewable operating permit as a result of a petition filed pursuant to 40 C.F.R. 70.8(d) after the department has issued the renewable operating permit, the department shall

    follow the procedure specified in 40 C.F.R.  70.7(g), adopted by reference in R 336.1299, to resolve the objection.

History: 1995 AACS; 1996 AACS; 2001 AACS; 2008 AACS; 2012 AACS.