Section 336.2156. Performance testing notifications; monitoring notification.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • Rule 1156. The owner or operator of any source required to install a continuous emission monitor by R 336.2101, R 336.2102, R 336.2103,  or  R 336.2104 shall submit to the department all of the following:

    (a)     A source-specific monitoring plan not less than 60 days prior to performance specification testing of the monitoring system for the review and approval of the department.

    (b)      A site-specific test plan not less than 30 days prior to the performance specification testing of the monitoring system for review and approval  of  the department.

    (c)      All results of performance specification testing not more than 60 days after the last date of the test.

History: 2009 AACS.