Section 408.30562. Submittal of documents.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • Rule 562.  Section 106.1 of the code is amended as follows:

    106.1       Submittal of documents. Construction documents, special inspection and structural observation programs, investigation and evaluation reports, and other data shall be submitted in 1 or more sets with each application for a permit. The construction documents shall be prepared by or under the direct supervision of a registered design professional when required by   1980 P.A. 299, MCL 339.101 to   339.2721.    Where

    special     conditions      exist,      the  building  official  is  authorized  to   require  additional construction  documents to be prepared by a registered design professional.

    Exception: The building official is authorized to waive the submission of construction documents and other data not required to be prepared by a registered design professional if it is found that the nature of the work applied for is such that reviewing of construction documents is not necessary to obtain compliance with this code.

History: 2002 AACS; 2008 AACS.