Section 460.20426. Leakage surveys.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  •  In addition to  the  requirements  set  forth  in  49  C.F.R.§192.706, which is adopted by reference  in  R  460.20606,  an  operator  of pipeline facilities used in the transportation of sour gas shall conduct leak surveys of those pipeline facilities using leak detection equipment at intervals of not more than 7 1/2 months, but not less than 2 times each calendar year, for all areas falling within the class 1 and class 2 location designations set forth in 49 C.F.R. §192.5, which is adopted by reference in R 460.20606.

History: 2003 AACS.