  • Final clean-up shall consist of removing the  temporary   haul road across the stream; reshaping the stream as nearly as possible to its original configuration, width, depth and bottom material; protection of the stream banks as specified in R 281.837; and removing all construction material and debris from the crossing site,  including  any  material    and debris downstream from the site as a result of the pipeline  construction.