Michigan Administrative Code (Last Updated: November 16, 2016) |
![]() |
Department EQ. Environmental Quality |
![]() |
Air Quality Division |
![]() |
Chapter Dry Cleaning Establishments |
![]() |
Part 5. BUILDING REQUIREMENTS |
Section 325.17510. Combustion air openings.
Latest version.
All data is extracted from pdf, click here to view the pdf.
-
(1) Nonpowered combustion air openings for fuel-fired unit space heaters, steam boilers, and water heaters shall be sized at ½ square inch of net free area per 1,000 Btu per hour input and 1 square inch net free area per 1,000 Btu per hour input for dryers.
(2) If powered combustion air supply equipment is used as an alternate to subrule
(1) of this rule for water heaters and boilers, then the powered combustion air supply equipment shall be selected to provide not less than 0.33 cubic feet per minute per 1,000 Btu per hour input and shall be electrically interlocked to the combustion controls of each unit.
History: 1981 AACS; 2004 AACS.