Section 408.30509. Frame and masonry inspection.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • Section R109.1.4 of the code is amended to read as follows:

    R109.1.4.   Frame  and  masonry  inspection.   Inspection   of    framing construction shall be made after the  roof,  all   framing,  firestopping, draftstopping, and bracing are in place and after the plumbing, mechanical, and electrical rough inspections are approved. Masonry inspections shall be made after the completed installation of base course flashing as specified in section R703.7.5 of the code and water-resistive barrier as specified in section R703.2 of the code and after the masonry construction is completed.

History: 2001 AACS; 2008 AACS.