Section 408.3911. Procedure on violations.


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • The following procedure shall be followed when a violation of these rules has been cited:

    (a)   Upon completion of the inspection of a construction project, each inspection report containing a violation of rules not corrected before the inspector leaves the site shall contain the date for correction of each violation.

    (b)   One copy of the inspection report shall be left at the job site with the employer's representative; 1 copy of the report shall be filed in the Lansing office and a record posted of any uncorrected violations; and 1 copy of the report citing violations and a compliance form or forms to be returned to the Lansing office shall be sent by first class mail to the registrant.

    (c)    The registrant shall return the form certifying compliance within 10 days after the required date of compliance. If the form is received by the department within the 10 days certifying that the registrant has corrected the violations, the file on the report shall be closed. If the registrant fails to return the form,  his   record  shall   be  posted  to show noncompliance.

    (d)   The department shall consider extensions of time for compliance upon receipt from a registrant of a request indicating progress to  date  and reasons for  an   extension of time. The department shall notify the registrant of its decision by first class mail, within 10 days.

    (e)   When the department determines that a violation exists which may result in serious injury, the department shall transmit such information to each individual commission member, and upon concurrence of a majority of the commission members, shall notify the registrant or employer to appear before the commission in accordance with section 11 of the construction safety act, Act No. 89  of   the  Public Acts  of  1963,  as amended, being S408.721 of the Michigan Compiled Laws.

History: 1979 AC.