(1) A class 1B installer's license qualifies a person to install a low- pressure boiler that does not exceed a firing rate of 1,000,000 BTU per hour as certified by the boiler manufacturer. For a class 1B license, the sum of all modules in a modular boiler shall not exceed a firing rate of 1,000,000 BTU per hour as certified by the boiler manufacturer.
(2) A class 2B installer's license qualifies a person to do all of the following:
(a) Install a low-pressure boiler of any capacity or firing rate.
(b) To perform work covered by a class 1B license.
(3) A class 3B installer's license qualifies a person to do all of the following:
(a) Install a power boiler that has a capacity of not more than 5,000 pounds of steam per hour.
(b) Install or replace non-boiler external piping as defined by ASME code B31.1 and R 408.4032.
(c) Perform work covered by a class 2B license.
(4) A class 4B installer's license qualifies a person to do all of the following:
(a) Install a boiler that has a capacity of not more than 300,000 pounds of steam per hour.
(b) Install or replace non-boiler external piping as defined by ASME code B31.1 and R 408.4032.
(c) Perform work covered by a class 3B license.
(5) A class 5B installer's license qualifies a person to do all of the following:
(a) Install a boiler of any capacity or firing rate. Exception: a nuclear heat source boiler.
(b) Install or replace non-boiler external piping as defined by ASME code B31.1 and R 408.4032.
(c) Perform work covered by a class 4B license.
(6) A class 6B installer's license qualifies a person to install a boiler that utilizes a nuclear heat source or its parts, appurtenances, or system components. Before a license is issued, an applicant for a class 6B license shall submit evidence of both of the following:
(a) Familiarity with and knowledge of all federal rules and regulations regarding the installation of a boiler that has a nuclear heat source.
(b) Employment by a company in possession of a valid ASME nuclear code symbol applicable to the portions of any nuclear boiler system that the company proposes to install.
(7) A class P license qualifies a person to install or replace non-boiler external piping or repair non-boiler external piping as defined by ASME code B31.1 and R 408.4032.
History: 1979 AC; 1995 AACS; 1998-2000 AACS; 2002 AACS; 2009 AACS.