Michigan Administrative Code (Last Updated: November 16, 2016) |
![]() |
Department LR. Licensing and Regulatory Affairs |
![]() |
Bureau of Construction Codes |
![]() |
Chapter Michigan Boiler Rules |
![]() |
Part 2. EXISTING INSTALLATIONS STEAM BOILERS |
Section 408.4241. Gauge cocks.
Latest version.
All data is extracted from pdf, click here to view the pdf.
-
Each power boiler shall have 3 or more gauge cocks, located within the visible length of the water glass, except when the boiler has 2 water glasses located on the same horizontal lines. Boilers not over 36 inches in diameter, in which the heating surface does not exceed 100 square feet, need have but 2 gauge cocks. For all installations where the water gauge glass or glasses are more than 30 feet above the boiler operating floor, it is recommended that water-level indicating or recording gauges be installed at eye height above the operating floor.
History: 1979 AC.