Section 408.4268. Feedwater connections.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • Feedwater,  make-up  water,  or  water  treatment  shall  be introduced into a boiler through the return piping system   or   through    an independent feedwater

    connection which does not discharge against parts of the boiler exposed to direct radiant heat from the fire. Feedwater, make-up water, or water treatment shall not be introduced through openings or

    connections provided for  inspection  or  cleaning,  safety   valve, safety-relief valve, surface or main blowoff, water column, water gauge glass, pressure gauge, or temperature gauge.

History: 1979 AC.