Section 408.7012. Temporary use of permanent elevators during construction.  


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • (1) A licensed  elevator   contractor  may  request  a   temporary certificate of operation to permit the use of a passenger or freight elevator before its completion for carrying workers, authorized personnel, or materials.   Such elevator shall not be used until it has been approved  by  a general  inspector,  the  required   fee  has  been

    paid, and a  temporary certificate of operation has been obtained.  Such certificate shall be issued for a period not to exceed 90 days. Renewals may be granted at the discretion of the department.

    (2)     Permanent elevators used temporarily during construction shall be inspected every 30 days.

History: 2003 AACS.