Section 460.144. Restoration of service.


Latest version.

All data is extracted from pdf, click here to view the pdf.

  • (1) After a utility has shut off service, it shall restore service promptly upon the customer's request when the cause has been cured or credit arrangements satisfactory to the utility have been made.

    (2)   When a utility is required to restore service at the customer's meter manually, the utility shall make every effort to restore service on the day the customer requests restoration. Except for reasons beyond its control, the utility shall restore service not later than the first working day after the customer's request.

    (3)     For utilities using meter technology with remote shutoff and restoration capability, service shall be restored on the day the customer requests restoration, except in the case of documented equipment failure.

    (4)   The utility may assess the customer a charge, including reasonable costs, for restoring service and relocating the customer's meter as specified in the utility's approved schedule of rates and tariffs.

History: 2007 AACS.