Michigan Administrative Code (Last Updated: November 16, 2016) |
Department LR. Licensing and Regulatory Affairs |
Public Service Commission |
Chapter Michigan Gas Safety Standards |
Part 4. SOUR GAS PIPELINES |
Section 460.20413. Underground clearances.
Latest version.
All data is extracted from pdf, click here to view the pdf.
-
In addition to the requirements set forth in 49 C.F.R.§192.325, which is adopted by reference in R 460.20606, an operator of pipeline facilities used in the transportation of sour gas shall, if practical, install the pipeline with not less than 48 inches of clearance from all other underground structures not associated with the pipeline. If this clearance cannot be practicably attained, the pipeline shall be protected from damage that might result due to its proximity to the other structure or structures.
History: 2003 AACS.