Michigan Administrative Code (Last Updated: November 16, 2016) |
![]() |
Department LR. Licensing and Regulatory Affairs |
![]() |
Public Service Commission |
![]() |
Chapter Electric Interconnection And Net Metering Standards |
![]() |
Part 2. INTERCONNECTION STANDARDS |
Section 460.628. Easements and rights-of-way.
Latest version.
All data is extracted from pdf, click here to view the pdf.
-
If an electric utility line extension is required to accommodate an interconnection, the applicant is responsible for the cost of providing or obtaining easements or rights-of-way.
History: 2009 AACS.